In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Sexually transmitted disease.
I need help with Math please
How does careless tourism harm corals?
which of the following are common safety equipment used to help you avoid serious injury? a. Helmet b. Protective eyewear c. All of a above
How many real solutions does p^2-5p+7=0 have
how can graphing help solve a problem involving ratios
How many cubic miles of water on Earth is stored as groundwater?
Which of the following is a characteristic typically not used to classify biomes? a. climate b. vegetation c. temperature d. geography Please select the b
Which of the following statements best describes carrying capacity? A. Carrying capacity is determined by a variety of environmental factors, and represents th
A way to write numbers by using the digits 0-9