A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

Calculate the molarity of each solution. 28.33 g c6h12o6 in 1.28 l of solution
___________ damages are compensation awarded to punish the defendant.
Is alcohol a gateway drug true or false
What Islamic ruler defeated the Hindu kingdom of Vijayanagar? A. Ali   B. Ismael   C. Babar   D. Akbar
Analyze the sentence to determine the main clause and the subordinate clause. Then choose the function of the subordinate clause. It is not right to make a prom
Does anyone know the answer Read the passage. excerpt from "My Aunt Gold Teeth" by V.S. Naipaul Ramprasad died early next morning and we had the announcement on
Please help . I really need help, and can't figure this out, Will mark you as brainliest !! Arrange the cylinders in order from least volume to greatest volume.
1.04 properties of water
please write me a paragraph on how DNA mapping is very important to evolution. 20 points
Which of these is MOST LIKELY to cause natural pollution?