15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

The Great Recession • In Chapter 29, read "The Great Recession" section and answer the following questions: 1. A boom in what industry set up the economy for an
What evidence indicates the type of transport that is occurring across this plasma membrane
I need help with this problem
To rename a worksheet, you change the text on the ? HELP ASAP A. Sheet Columns B. Sheet Header C. Sheet tab
Mia paints interior walls at a rate of 12 m^2/h. At what rate does Mia paint in cm^2/min?​
PLEASE ANSWER AN GIVE SOLUTIONS
Solve the following system of equations.
A student adds 50 ml of water to a graduated cylinder and then drops into the graduated cylinder to find the volume. What is the volume of just the rock?
Evan can run 4 kilometers in 20 minutes. At this rate, how far can Evan run in 1 minute? *
what needs to be done to make nepal a developed country