A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time

Respuesta :

andromache andromache
  • 04-06-2021

Answer:

9

Explanation:

Given that

There is five stations who have the process time of 5,9,4,9 and 8

We need to find out the bottleneck time

so, as we know that the bottleneck is the duration of the activity who have longer time

So as per the given situation the 9 has the longest duration activity time

So, the same is to be considered

Answer Link

Otras preguntas

MRP II is accurately described as-
Two numbers have a sum of 71 and a difference of 37 (PLEASE HELP ME,MY TEACHER HATES ME)
An essay that uses first, next and finally indicates what type of organization? A. Cause and effect B. Example and explanations C. chronicall order D. Compariso
In what year did the British raj’s rule end in India?
what indicates wind direction
How did the Bay of Pigs invasion strengthen Castro's power in Cuba?
What is a coordinating conjunction?
The amount of a person’s paycheck p varies directly with the number of hours worked t. For 22 hours of work, the paycheck is $126.50. Write an equation for the
11.9x+10.5y=178.5 Help me please
The tendency of molecules to move toward areas of lower concentration is called _____. a. suffusion b. diffusion c. suspension d. effusion