A can do a piece of work in 20 days and B can do it in 12 days,B work for 9 days,in how many days A alone can do the work​

Respuesta :

roseheart889 roseheart889
  • 03-09-2020

Answer: 9

Step-by-step explanation:

Answer Link

Otras preguntas

It is not safe to put a child in a bathtub without first adding bubbles. True False
jimthompson5910 is such a great help and so important in making a differnce here. A given line has the equation 2x + 12y = −1. What is the equation, in slope-in
How many triangles can be formed if in triangle ABC, b=120, c=92 and C=42°?
What did the Monroe doctrine prohibit European countries from doing
AP Psych Which language theorist would have been most likely to emphasize that children master the rule for forming the past tense of regular verbs like "push"
Instructions:Select the correct answer. Whose unexpected reaction after one of George Whitefield's sermons demonstrated how powerful Whitefield's preaching styl
What force do the brakes exert on the cart?
look at number 17. What did I do wrong?
Place a check next to all the problems that the abuse of alcohol was creating and ultimately led Americans to favor prohibition of alcohol. Lower productivity
The reign of alexander ii came to an end in 1881 when he __________. a. abdicated b. died from natural causes c. was assassinated d. was overthrown by a cou